Question

Refer to the exhibit! What is the output payload in the On Complete phase?


Answer

A) Summary statistics with NO record data
B) The records processed by the last batch step: [StepTwo1, StepTwo2, StepTwo3]
C) The records processed by all batch steps: [StepTwostepOne1, stepTwostepOne2] [StepTwoStepOne3]
D) The original payload: [1,2,3]

The correct answer to this question is A.

Explanation

According to MuleSoft, during the On Complete phase, you can optionally configure the runtime to create a report or summary of the records it processed for the particular batch job instance. This phase exists to give system administrators and developers some insight into which records failed to address any issues that might exist with the input data, so the correct answer is A.